I am scheduling a project that will be executed in two shifts.
Any of the tasks can be performed by either the day shift or the night
shift. Incomplete tasks can be turned over from one shift to the next.
Several tasks are being peformed in parallel by the same resources (e.g.
millwrights).
Is there any way that I can specify a resource calendar with different
number of resources per shift (e.g. 6 day shift, 5 night shift)?
Creating different resources for day shift and night shift, as has been
suggested in other threads, will not work as I do not know up front which
tasks will be performed during day or night shift.
TIA
Pius Frei
Any of the tasks can be performed by either the day shift or the night
shift. Incomplete tasks can be turned over from one shift to the next.
Several tasks are being peformed in parallel by the same resources (e.g.
millwrights).
Is there any way that I can specify a resource calendar with different
number of resources per shift (e.g. 6 day shift, 5 night shift)?
Creating different resources for day shift and night shift, as has been
suggested in other threads, will not work as I do not know up front which
tasks will be performed during day or night shift.
TIA
Pius Frei