Hi i thought i was ready to get everybody to use project server until i did a
demo with my organisation. They raised the question of versions! They wanted
to know if they could replace a published plan with one of it's versions. So
someone opens up a a published project and saves it as for example version 2
so they can display a whatif scenario. After doing all this could they go
back and use their whatif scenario as their main published plan?
Also i have noticed that any projects that i put on the server from previous
versions of project i.e project 2000aren't the same - the days on the gantt
charts get changed to decimals. so 29days may become 29.4days. I tried
changing the working time section -this hasn't helped!
If anybody could help me i would be most thankful.
demo with my organisation. They raised the question of versions! They wanted
to know if they could replace a published plan with one of it's versions. So
someone opens up a a published project and saves it as for example version 2
so they can display a whatif scenario. After doing all this could they go
back and use their whatif scenario as their main published plan?
Also i have noticed that any projects that i put on the server from previous
versions of project i.e project 2000aren't the same - the days on the gantt
charts get changed to decimals. so 29days may become 29.4days. I tried
changing the working time section -this hasn't helped!
If anybody could help me i would be most thankful.