Anasepm:
Tools > Tracking > Baseline - You can view this information the same way you
set the baseline provided that you use a method to preserve the dates. My
favorite way to do this is to save the first baseline to Baseline and
Baseline10. Then when I change the baseline, I save it to Baseline and
Baseline9. This way you can see the baseline history. If you simply save
over the baseline, this information is not preserved in the system.
--