versioning of Project Schedule

N

nauman1278

Do project server 2007 save different versions of project schedule as
it updates them...
Or it only have one version of project schedule.
 
J

James Fraser

It only maintains a single instance of each project.

Paul is correct.

Many people who want versioning might like the multiple baselines
allowed. Half of these can have limited access in Project Server 2007.

Also, the automatic backup function of Project server 2007 can be set
to store multiple versions of projects. Of course, this will grow your
archive database considerably.


James Fraser
 