We are using Project Server 2002 and are experiencing two issues with a
single plan posted to the server that has over 2000 tasks. The issues are:
1) Extremely slow saves when saving/publishing the plan to the server (5
minutes or more).
2) Tasks in the plan that have actuals applied to them and remaining work
has been zeroed out, predecesors are also complete are not displaying as
complete (100% shows, but now Check mark).
Any suggestions on what to look for to correct these issues?
Thanks,
Ti
We are using Project Server 2002 and are experiencing two issues with a
single plan posted to the server that has over 2000 tasks. The issues are:
1) Extremely slow saves when saving/publishing the plan to the server (5
minutes or more).
2) Tasks in the plan that have actuals applied to them and remaining work
has been zeroed out, predecesors are also complete are not displaying as
complete (100% shows, but now Check mark).
Any suggestions on what to look for to correct these issues?