Hi all,

In my schedule, there are many tasks is linked.
Eg:

ID Task Name Predecessor
1 Task 1
2 Task 2 1
3 Task 3 2
4 Task 4
5 Task 5 3
6 Task 6 5

With a task, I need to view all tasks link to it. In the examples above, I
select Task 6, and I need to view all task to which Task 6 depends: Task 1,
2,3,5. Is there a view to do that?
Thanks
 