View Assignments frustration

J

jbigroups

For three project schedules we have items in "View Assignments" that
show incomplete/past due, but in each project it shows 100% complete in
July. I have republished the info (and every other publishing option)
with no improvements.

Also when I look at the data from the tables I can't find where that
info is stored. The dbo_MSP_VIEW_PROJ_ASSN_STD table shows 100%. Any
suggestions on how to fix? And which table?

Thanks for the help

jb
 
D

Dale Howard [MVP]

jb --

When you say you republished the info, did you click Collaborate - Publish -
Republish Assignments, select the "Overwrite actual work entered by
resources" option, and then click OK?
 