M
Mauricio@BVFG
Hi Gurus!
I have the following RBS defined in Project:
Level 1: CIO,
Level 2: DB Manager
Level 3: SQL DBA
Level 3: Oracle DBA
Level 2: VP IT Ops
Level 3: Manager a
Level 3: Manager b
I have defined a view on Project Center only to show projects assigned to VP
IT OPS' resources (i.e. Manager a and Manager b). Why the view is showing
projects managed by staff that are not within the same RBS authority (i.e. DB
Manager)?
Thanks
I have the following RBS defined in Project:
Level 1: CIO,
Level 2: DB Manager
Level 3: SQL DBA
Level 3: Oracle DBA
Level 2: VP IT Ops
Level 3: Manager a
Level 3: Manager b
I have defined a view on Project Center only to show projects assigned to VP
IT OPS' resources (i.e. Manager a and Manager b). Why the view is showing
projects managed by staff that are not within the same RBS authority (i.e. DB
Manager)?
Thanks