View multiple assignment-level baseline costs

K

KingKikapu

Is there any way to see more than one baseline cost for an assignment i
the same view?

I wish to visually compare Baseline with Baseline 9 and 10 fo
assignments all at once. Is this possible
 
K

KingKikapu

Actually, I think I might have spotted the solution: I can add th
necessary columns to the Task Usage view. Go me!


:
 