View My Task doesn't update when saving projects

A

Anon

In Project Server 2003, I updated and saved my project
back to the server with Project 2003 Pro. The
completion percentages that I entered in Pro did not show
up in the View My Task screen, even though they did show
up for the task over in the Project screen. What am I
doing wrong? Is there a prodcess that hss to run
periodically to update the "View My task" page?
 
D

Dale Howard

Anon --

If you entered the percent complete values in the project plan in Microsoft
Project 2003, rather than in the View My Tasks page in Project Web Access,
then you need to republish your assignments. To do this, open the project in
Microsoft Project and then click Collaborate - Publish - Republish
Assignments. In the dialog box, check the "Overwrite actual work entered by
resources" option and click the OK button. This will "push" your percent
complete values from the project plan to your View My Tasks page. Hope this
helps.
 