view my tasks date units

L

lynne baker

please can you tell me if it is possible to set the date units to
always show in "days" rather than "weeks"?
My chaps can change the default of weeks to days, but this is not
remembered once they log out. Is there a way of setting this somewhere
- or an alternative method of keeping that setting?
Thanks
lynne
 
D

Dale Howard [MVP]

lynne baker --

The date units value for every user's timesheet is set by the Project Server
administrator, and will need to be changed by completing the following
stesps:

1. Log into PWA with administrator permissions
2. Click Admin
3. Click Customize Project Web Access
4. In the Time Period Settings section of the page, select the "Resources
should report their hours worked every day" option
5. Click the Save Changes button

Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
L

lynne baker

Thanks so much Dale - I happened to find that setting just after posting!
It works perfectly
Many thanks again for responding - you're a wonderful resource!
lynne
 
D

Dale Howard [MVP]

lynne --

You are welcome, my friend! :)