I am not sure I understand your question. I assume you have already created
the master project by inserting the subprojects or by creating the
consolidated project through the resource pool.
To show all tasks, click the Task Name column heading and on the Formatting
toolbar click the Show drop down and select All subtasks.
I am not sure I understand your question. I assume you have already created
the master project by inserting the subprojects or by creating the
consolidated project through the resource pool.
To show all tasks, click the Task Name column heading and on the Formatting
toolbar click the Show drop down and select All subtasks.
Octavia,
Just an added note to what Julie wrote. If you then save the master file
in its fully "exploded" state, it will appear that way the next time you
open it.
John