P
Pete Chrisbacher
Hello all -
Using MPS 2003, MPP 2003
Logged into PWA as a Project Manager, in Resources=>View Timesheet
Summary=>Timesheet View it appears PWA is "losing" the last task for all
displayed resources.
E.g. If the actual timesheet looks like this:
Task 1
Subtask 1
Subtask 2
Subtask 3
The Timesheet Summary view will show:
Task 1
Subtask 1
Subtask 2
This happens consistently for all resources (we only have two in the current
plan). As it happens, we've only noticed this since approving the
timesheets for these resources, but it may have been the case prior to
approval - not sure.
Anyone else experience this? Is it a known bug? Is this just a display
problem, or is there actual data corruption happening behind the scenes?
I'll investigate further to see what I can figure out (likely tomorrow or
Monday ;-) - but I figured I'd post in the mean time in case someone else
had seen this before.
Thanks -
-Pete
Using MPS 2003, MPP 2003
Logged into PWA as a Project Manager, in Resources=>View Timesheet
Summary=>Timesheet View it appears PWA is "losing" the last task for all
displayed resources.
E.g. If the actual timesheet looks like this:
Task 1
Subtask 1
Subtask 2
Subtask 3
The Timesheet Summary view will show:
Task 1
Subtask 1
Subtask 2
This happens consistently for all resources (we only have two in the current
plan). As it happens, we've only noticed this since approving the
timesheets for these resources, but it may have been the case prior to
approval - not sure.
Anyone else experience this? Is it a known bug? Is this just a display
problem, or is there actual data corruption happening behind the scenes?
I'll investigate further to see what I can figure out (likely tomorrow or
Monday ;-) - but I figured I'd post in the mean time in case someone else
had seen this before.
Thanks -
-Pete