view % work completed

D

dee

Dear all,
I want to ask bout this :
In gant cart view, it was displayed in % format, but If I create report
using visual report, like examples, I choosed New Template - Task Usage, the
column % work completed display 0,97. How must I do to change in format (97%)

Regards,

dee
 
D

Dale Howard [MVP]

Dee --

Again, your question implies you are using Project 2007. When you talk
about the Visual Report you created, I assume right-clicked on the Project
Summary Task, selected "Show Properties in Report" from the shortcut menu,
and then selected "% Complete" on the flyout menu. This action inserts the
% Complete field in the PivotTable to the right of each task, but formats
each number in the % Complete field using the General number format and not
as a percentage. To resolve this problem, right-click on the column header
of the column containing the % Complete values and then select "Format
Cells" from the shortcut menu. In the Format Cells dialog, select the
Number tab if necessary, and then select the Percentage format. In the
Decimal Places field, select the number of decimal places to display in the
percentage value and then click the OK button. Hope this helps.
 