G
Glenn
Previously, I successfully had setup a tracking gantt line which showed up in
red.
The line moved vertically up and down my gantt chart starting at the current
date. If it came to a task that was not yet complete and behind schedule, it
would draw a line from the current date to the task current status date.
My problem is that I can no longer remember how I did this. I have my
current projects schedule with a saved baseline. I am viewing my tracking
gantt view but no line is visible.
Thanks for any heads up out there.