Viewing a Slipped Schedule ?

G

Glenn

Previously, I successfully had setup a tracking gantt line which showed up in
red.

The line moved vertically up and down my gantt chart starting at the current
date. If it came to a task that was not yet complete and behind schedule, it
would draw a line from the current date to the task current status date.

My problem is that I can no longer remember how I did this. I have my
current projects schedule with a saved baseline. I am viewing my tracking
gantt view but no line is visible.

Thanks for any heads up out there.
 
G

Glenn

Sorry folks. I just found what I did. The line I was referring to is called
a progress line. Simply go to Tools ! Tracking | Progress Lines
 