Viewing Calc. Text Fields in PWA & MSProject But not in DB

B

BayerWhite

Calc. Text fields can be seen in PWA and MSProject because they both use the
formula to calculate the field, however this value is not in the
MSP_TEXT_FIELDS table until the project is actually saved using PWA or
MSProject.
My group was trying to bounce the calc. text value to a outline code to be
viewed in the OLAP cubes, yet I could not get the calc. value from the db
that PWA and MS Project was showing.
 
R

Rod Gill

Nothing gets updated in the database until a project is saved, PWA posts
timesheets or the project is published.

Try the MSP_VIEW tables for reporting purposes.
 