viewing master schedule with PWA

R

Ryan

Is it possible to view the details of a master schedule from PWA? We can
currently view all the subdirectories under the master schedule but none of
the actual data that is in them. Is this a limitation of pwa? Is there some
other recommended best practice for this? Thank you in advance for any
assistance.
 
D

Dale Howard [MVP]

Ryan --

No, you cannot view the details of a master project inside of PWA. You can
see the details by opening the master project in Microsoft Project
Professional. Hope this helps.
 