Viewing plans in PWA

K

kc

I know that a resource has to be assigned to a task in
order to access the subweb. But does a resource have to
be assigned to a task in order to view the project in
PWA? Or is it enough to add him to the project team from
the ERP?
 
S

Sumit

Dear KC,

Adding a resource to resource sheet is enough to enable him access project
in Project Center.

Regards,
Sumit
 
Top