Darla --
If you want to see the timesheet on each user's View My Tasks page, then the
answer is no. On the other hand, you can see something similar in the
Resource Center. Try the following and see if this will suffice for your
needs:
1. Log into PWA as Administrator
2. Click the Resources menu
3. Click the View Resource Assignments link
4. In the sidepane on the left, select the Timesheet format link
5. In the sidepane on the left, select the All Assignments link
6. Collapse the sidepane on the left to see more of the data grid
7. On the Filter, Group, Search tab set grouping to Resource and then by
Project
You should now see the combined timesheets for all your resources. Just an
idea. Hope this helps.