J
jason
3 q's
What view do I need to go to see a visual if tasks are
sliding or ahead of schedule?
Also, when filling out a time sheet on a task that is
stretched out for a few weeks, let's say 4 hrs a day is
scheduled, but that day she only works three hours, does
that hour add to the rest of the time to bump it up 4.10
hrs per day now?
Last, as a pm, when I accept work or status updates in
PWA, it is really hard for me to see how it will affect my
schedule, before it automatically saves. Is there a way to
not save the plan before seeing what the actual work did
to my project plan?
Thank you,
Jason
What view do I need to go to see a visual if tasks are
sliding or ahead of schedule?
Also, when filling out a time sheet on a task that is
stretched out for a few weeks, let's say 4 hrs a day is
scheduled, but that day she only works three hours, does
that hour add to the rest of the time to bump it up 4.10
hrs per day now?
Last, as a pm, when I accept work or status updates in
PWA, it is really hard for me to see how it will affect my
schedule, before it automatically saves. Is there a way to
not save the plan before seeing what the actual work did
to my project plan?
Thank you,
Jason