Views Notification Service Errors

T

Tim

We have been having an issue with this for quite some time
and have not been able to resolve (Proj Server 2002,
EditSite with 3 instances (2 prod, one test, only 1 prod
instance actively used). Have tried solutions in KB #s
81059, 837154 with no luck (ViewDrop folder permissions
are set). The latter is regarding list separator chars in
resource names that foul up OLAP cube generation. Found
half a dozen resources with such chars, fixed and
resources did not sync (app log entry follows of error
after update). There are about 2 dozen resources added in
the past month that have not synced. In the past, when
project info has not been updating in views, restarting
the server sometimes solved the problem. Not so anymore.
Any ideas?
Thanks, Tim.


Event Type: Error
Event Source: Microsoft Project Server Tracing Eventlog
Provider
Event Category: None
Event ID: 2
Date: 7/13/2004
Time: 9:24:23 AM
User: NT AUTHORITY\SYSTEM
Computer: PROJOFF
Description:
Component: PCSViews
File: ViewsDrop.cls
Line: -1
Error Number: 0x5
Description: Error Information: Invalid procedure call or
argument
Additional Information: An error occured processing the
following view :-

<ViewsDropData>
</EntProjectName>
<EntResourceIDList>1</EntResourceIDList>

<EntResourceStartDate>7/13/2004</EntResourceStartDa
te>

<EntResourceFinishDate>8/10/2004</EntResourceFinish
Date>
</ProjectData>
<OrgGuid>projectserver</OrgGuid>
<BasePath>projectserver</BasePath>
<TimeStamp>7/13/2004 9:24:23 AM</TimeStamp>
</ViewsDropData>
 