WA Save hours

E

Erkki Piipari

Hi again.

In WA the user has an option not to send the task actual
hours immediately to the project manager. The help says:

"To save the changes you just made, but not submit the
updates to your project managers, click Save Changes"

In some instances though, the systems sends the updates at
once. Has anybody seen this "bug" before ? Are there
perhaps other factors to consider, like categories or
parameters.

Thanks again for your support.
PS Gary,if you read this, I'm the guy who bought the
book :)

Erkki
 
G

Gary L. Chefetz [MVP]

Erkki:

Delegations and task rejections send immediately no matter what you do.
Hours reported and new tasks should update to the PM only when the Udate
button is pressed.
 
Top