weekend dates

A

Amy

We are attempting to creat a Gant chart. We have to
include weekend dates. Even with all 7 days checked as
available, it reverts back to a weekday date. Any help?
 
M

mgk

how about :

Set the non-working days in a Gantt chart
In a Gantt chart, right-click any part of the timescale,
and then click Configure Working Time.
Choose the options you want, and then click OK.



ok?
 
Top