weird problem about viewing "my tasks" -workaround included-

O

orkun goze

hi all,

i am having a weird situation about viewing tasks assigned to a resource in
the project server.

the situtation:
i imported and published a project from project professional with the
resources that have assigned tasks.
then i logged in the project web access and checked that the project, the
tasks and resources are all ok.
then i created user accounts for the resources in the project server
enviroment.
the problem is; when i log in the project web access as a resource, i can
not see any task under "my tasks". but when i log in as project manager i can
see that there are tasks assigned to that spesific resource.
this is same for all resources that are imported from project professional.


the workaround:
if i create the resource first in project server, and then map it with the
appropriate resource from the project professional while importing the
project, it works just fine. i can see all the tasks assigned to the resource
when i log in as that resource.
but if i let the system create resources on the server side during import,
it causes the problem.

i dont want to do duplicate work by creating the resources manually both on
the professional and server sides. so i will appreciate any thoughts about
this problem.


note: it is not about user rights. i assigned all administrator rights to a
resource to see if it works but it did not.


regards,
orkun
 
S

Sébastien Pouliot

hi,
Try to to create user accounts for the resources in the project server
enviroment before import it into your Project. If this solution not work,
try to republished all informations (in Collaborate Menu).

Hope this helps...
 
O

orkun goze

hi sebastien,

creating user accounts before import did not work for me.
i could not find any "publish" function under collaborate menu (project pro
2007). and the "publish" under the file menu did not work either...

any more thoughts?

thank you
orkun
 