Alfred -
There are two ways to answer this question - from the point of
Microsoft Project, and another from the point of WBS.
From the point of Microsoft Project, Level 1, Level 2, ..., represents
the level number present in the "Outline Level" field. You can try
creating summary tasks, and insert a column with the field name
"Outline Level". You would observe the project summary task (if you
have selected it in Tools | Options, View tab, Show Project Summary
task) has the outline level value has 0, and summary tasks in first
level will be with outline level value 1, and so on.
Now from the point of WBS development, which is a key input for
schedule development. Upper levels (lower id) represents the major
work areas or the major phases of the project. So, the summary tasks
with outline level value 1 or 2 should mostly be features of the
product/service, followed by the phases required to deliver the
product. The lower levels (higher ids) represent the work package
(that includes the tasks, estimated duration, estimated cost and
resources to create the deliverable).
Please let us know if this response is sufficient.
Regards
Sai
Website:
http://saipower.wordpress.com/