Hello,
I need to do what if scenario on the master plan we have.
The problem is when you have inserted projects in the master, when you
change a task within project A that has a Successor in project B,
Project B will not be updated unless I will close the master, open
project B and update the changes and than reopen the master.
What are my option regarding seeing updates in-between projects and
doing scenarios on the master.
Does project 2007 solves it?
Thank you very much.
I need to do what if scenario on the master plan we have.
The problem is when you have inserted projects in the master, when you
change a task within project A that has a Successor in project B,
Project B will not be updated unless I will close the master, open
project B and update the changes and than reopen the master.
What are my option regarding seeing updates in-between projects and
doing scenarios on the master.
Does project 2007 solves it?