Hello,
I need to do what if scenario on the master plan we have.
The problem is when you have inserted projects in the master, when you
change a task within project A that has a Successor in project B,
Project B will not be updated unless I will close the master, open
project B and update the changes and than reopen the master.

What are my option regarding seeing updates in-between projects and
doing scenarios on the master.

Does project 2007 solves it?
Thank you very much.
 
M

Marc Soester [MVP]

David have you tried having all projects open at the same time? I would think
that this would change the Master plan. ( I may be wrong since I have not
tried it, but may be worth giving it a go)
 
D

David.Rot

David have you tried having all projects open at the same time? I would think
that this would change theMasterplan. ( I may be wrong since I have not
tried it, but may be worth giving it a go)

--
Marc Soester [MVP]
State Manager: EPMhttp://marcsoester.blogspot.com







- Show quoted text -

Hey,
Thank you for your reply.
I found that I had a circular relationship in one of the in between
project I have.
Ones I have fix that I could make changes between the schedules and
see the affect.

Thank you very much,
David
 