MS Project Server 2003 SP-1
We would like to anticipate what the finish date/s might be for an
enterprise project if we were to increase the standard work day from 8 hours
to 10 hours.
Increasing the hours per day in the local base calendar for the enterprise
project does not affect the Finish values for any of the Tasks. Is there a
provision for doing what if scenarios such as this? Or, would we have to
resort to creating a (new) 10 hour enterprise calendar and then building
another project that uses the new enterprise calendar to assess the
difference in Finish dates?
Thank you.
We would like to anticipate what the finish date/s might be for an
enterprise project if we were to increase the standard work day from 8 hours
to 10 hours.
Increasing the hours per day in the local base calendar for the enterprise
project does not affect the Finish values for any of the Tasks. Is there a
provision for doing what if scenarios such as this? Or, would we have to
resort to creating a (new) 10 hour enterprise calendar and then building
another project that uses the new enterprise calendar to assess the
difference in Finish dates?
Thank you.