Project Enterprise Text30-40, Task Enterprise Text37-40, Task Enterprise Number 39&40. Thanks!
M Matt Mar 24, 2005 #1 Project Enterprise Text30-40, Task Enterprise Text37-40, Task Enterprise Number 39&40. Thanks!
N Nico Oosthuysen Mar 29, 2005 #2 hello, these are all stored in the tables called MSP_CUBE_ENTERPRISE_ASSIGNMENT_OUTLINE_XX (for tasks), MSP_CUBE_ENTERPRISE_PROJECT_OUTLINE_XX (for projects) and MSP_CUBE_ENTERPRISE_RESOURCE_OUTLINE_XX (for resources) where XX is the number.