I have multiple jobs numbers that have roughly 40 tasks to each one of the
jobs. I would also like to have a my job number visible at all time. What do
you think can this be done? What kind of template would you use?
Thanks for your time.
 
J

John

Dave W. said:
I have multiple jobs numbers that have roughly 40 tasks to each one of the
jobs. I would also like to have a my job number visible at all time. What do
you think can this be done? What kind of template would you use?
Thanks for your time.

Dave W,
The easiest thing to do is to use a spare text field to show your "job
number" and then include that text field as a column in your view(s).

John