We were able to Custumize the Published fields
(Tools>Customize>Published Fields...) to include the
Baseline Work(Assignment) in both the Tasks page for the
resource and the Updates page for the PM to compare
Baseline Work vs Work. We also had to get the admin to
modify the view in Web Access so that Baseline work
appears on the Assignment views (Tasks Page and Updates
Page)
I'm not sure if the field you are using for WBS exists at
the assignment level.
Search the list of 'Available Fields' under
Tools>Customize>Published Fields... and see if you can
push the desired field.
Hope this helps.
Piero
-----Original Message-----
Dale, Thank you for your reponse. It is unfortunate
that the view for Updates cannot be modified. This now
forces everyone to uniquely name tasks in order to avoid
confusion. I thought that was what WBS was for. Also,
why did Microsoft put in a ton of modifiable views and
then leave off the ONE view that is used MOST OFTEN by
project members? This kind of oversite drives me nuts!