C
Crabby
I have a project file with two milestone groups; each milestone has a few
mini-projects, and each mini-project has a handful of tasks. I am trying to
have milestone #2 start w.r.t. the end of milestone #1, and when I establish
the link, all but one of the mini-projects shifts its start-date accordingly.
The only thing about the non-conforming mini-project that's different is
that it has one task that it has one task that can't start until a task in
another miniproject in the same file and milestone group is completed.
Otherwise, all the tasks and the mini-projects start ASAP, without constraint.
mini-projects, and each mini-project has a handful of tasks. I am trying to
have milestone #2 start w.r.t. the end of milestone #1, and when I establish
the link, all but one of the mini-projects shifts its start-date accordingly.
The only thing about the non-conforming mini-project that's different is
that it has one task that it has one task that can't start until a task in
another miniproject in the same file and milestone group is completed.
Otherwise, all the tasks and the mini-projects start ASAP, without constraint.