B
Bucky Goldstein
When I print the report the to do list it shows tasks scheduled for non
working days.
working days.
JulieS said:Hi Bucky,
Are you sure the resource's have those days as nonworking in their
calendar? Display the resource sheet and double click on the
resource's name. Click the working time tab and double check their
working time schedule. If you've created a custom calendar for the
project you may also wish to double check that the project calendar
is set as the resource's base calendar. Check the Base Calendar
field in the resource sheet view.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
in message