When printing, the timescale starts way earlier than my project.

T

TFNGC

I did use an old project and changed it, but I have changed the project start
date and everything else I can think of. The timescale begins on the right
date on my screen when I am editing my project, but the print preview has the
timescale starting years ealier.
 
M

Mike Glen

Hi TFNGC,

Welcome to this Microsoft Project newsgroup :)

You could try running the Adjust Dates macro in the Analysis Toolbar. You
could also try selecting Print and in the print dialog select a suitable
date range.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
Top