Who does what when over various projects?

V

Volkmar

Hi,

I know there is a standard report "Who does what when?" in MS Project. What
I would need is a similar report over various projects, including the
dimensions resource, project and time.

Is this possible in MS Project or do I need a data cube in Project Server to
achieve this?

Thanks a lot.

Volkmar
 
R

Rob Schneider

Volkmar,

Assuming the various projects are in individual files, if you were to
insert them (with or without links) into a master file, and then use the
Task Usage and/or Resource Usage views -- does this fit the need?

--rms
 
R

Rob Schneider

Volkmar

Forgot to mention also, try out the Grouping capability in Project to
get some interesting views.

--rms
 