Arun --
To accomplish this with the Who Does What When report, you will need to use
a couple of tricks. First, because you wish to see every task assignment
those % Work Complete is greater than 0% for each resource (actuals booked
for the task), you will need to create a custom Filter by completing the
following steps:
1. Open the project in question
2. Click Project - Filtered For - More Filters
3. Select the Resources - Work filter and click the Copy button
4. Rename this filter something like "_msPE Work Resources with In Progress
Tasks"
5. Add the following information to the second line of the filter criteria:
And % Work Complete Is greater than 0
6. Click OK and then click the Close button (not the Apply button)
Second, you will need to select this new Filter in your Who Does What When
report definition. To do so, complete the following steps:
1. Click View - Reports
2. Double-click the Assignments section
3. Click the Who Does What When report and click Edit
4. Change the Filter selection to your new filter
5. Click OK
6. Double-click the Who Does What When report and examine the print preview
page
Lastly, you will need to set the date range in the Print dialog box by
completing the following steps:
1. While in Print Preview mode for this report, click the Print button
2. In the Timescale section of the Print dialog, set the From and To dates
3. Click the Preview button to make certain the date range is correct
If you wish to use this new Filter and Report for every existing project,
you will need to copy both of them to your Global.mpt file using the
Organizer (Tools - Organizer). If you wish to distribute these across the
enterprise, you should ask your Project Server administrator to create them
in the Enterprise Global file. Hope this helps.
Arun said:
Hi,
is there any way that i can show only the tasks which have actuall booked
for the date range that i specify.
Now when i take the above said report...i can see the list of tasks
assigned to the resource & the actual work put against each task on day
basis is shown.
Since the task list is so huge i see all the task irrespective of actuals
booked or not. I want to restrict this report to display only the task which
have actuals booked.