Who is the manager of the task?

R

Rene

In the PWA project view (list of task for one project), is
there a way to know who is the manager of each project
tasks.
This is the case where many managers publish specific task
in the same project by using "become manager of these
assigned".
 
D

Dale Howard

Rene --

The Manager of each task is the person who actually published the task
assignment to PWA, either by clicking Collaborate - Publish - New and
Changed Assignments, or clicking Collaborate - Publish - Republish
Assignments. The Manager is also the person to whom task updates are
directed in PWA.

The Manager column is viewable on each team member's View My Tasks page.
Project Center views can contain the Manager column as well, however, this
column shows only the person who intitially published the task assignments
in the project. It is not possible to add the Manager column to either a
detailed Project view or to an Assignment view. Sorry. Hope this helps.
 
G

Gary L. Chefetz [MVP]

Rene:

In addition to Dale's advice, you can see this information in the View
Resource Assignments view accessed from the Resource Center in Project Web
Access.
 