Why can't I update WBS Predecessor field?

L

LMMBLS?

I believe that when I first added the WBS Predecessor field to my GANTT chart
I could enter either a predecessor or a WBS Predecessor for a task. Now I am
completely unable to make any updates to the WBS Predecessor field. It seems
to be only derived and not directly enterable.
 
J

John

LMMBLS? said:
I believe that when I first added the WBS Predecessor field to my GANTT chart
I could enter either a predecessor or a WBS Predecessor for a task. Now I am
completely unable to make any updates to the WBS Predecessor field. It seems
to be only derived and not directly enterable.

LMMBLS,
We answered this question last week. Take a look at the thread for your
post on Oct 6.

John
Project MVP
 