S
sbardon
Microsoft Project 2007 (2003 file format)
Hi,
I have a task that has more than 256 characters worth of predecessors in
the predecessor field. Project is truncating the field and I canot copy out
the entire character list.
The task has and issue and I am trying to trouble shoot it. How do I
export, copy, anything to get the complete set of text from the Predecessor
field????
Thanks,
S
Hi,
I have a task that has more than 256 characters worth of predecessors in
the predecessor field. Project is truncating the field and I canot copy out
the entire character list.
The task has and issue and I am trying to trouble shoot it. How do I
export, copy, anything to get the complete set of text from the Predecessor
field????
Thanks,
S