Why can't see actual work?

  • Thread starter Mindaugas Bliûdþius
  • Start date
M

Mindaugas Bliûdþius

hi

i imported project (withc have some actual values alredy entered) to project
server. But in task view (timesheet) i can see only overall actual work done
for that task but there is no values in act.work fields (i whan to see day
per day) :(

Is there somewhere option hidden for this?
 
D

Dale Howard [MVP]

Mindaugas --

Open the project, click Collaborate - Publish - Republish Assignments,
select the "Overwrite actual work entered by resources" and then click OK.
This should solve the problem. Hope this helps.
 
M

Mindaugas Bliûdþius

Thank's it worked!

Dale Howard said:
Mindaugas --

Open the project, click Collaborate - Publish - Republish Assignments,
select the "Overwrite actual work entered by resources" and then click OK.
This should solve the problem. Hope this helps.
 
Top