T
Tomas Gendron
Hello, I have a submitted timesheet with hours on task 1 and task 3. Task 2
had hours and then was deleted. The timesheets shows 4hrs.
The timesheet was submitted and imported into "My Tasks". The hours I had
entered into Task 2 show up there even though I "deleted" them. There are 6
hrs instead of the 4 on the timesheet.
Any idea why? Thanks
had hours and then was deleted. The timesheets shows 4hrs.
The timesheet was submitted and imported into "My Tasks". The hours I had
entered into Task 2 show up there even though I "deleted" them. There are 6
hrs instead of the 4 on the timesheet.
Any idea why? Thanks