Nock
Hi,
For some reason my project start and finish dates keep reverting to '1984'
based dates...e.g '1/2/1984'
Anyone know why this is happening? I've seen this behaviour in previous
versions of the product (like MSP 98) but thought this would have been
resolved in 2007.
To recreate this error.
1. Create a new task in MSP and do not specify a start and finish date
2. Attach a precedessor to the task
3. Click save
4. Delete the predecessor and voila! Dates revert to xx/xx/1984.
I've notice that this behaviour appears for some users and not others, which
is a real pain. I've worked through the differences in the MSP options but
nothing seems to stick out.
All users are using MSP 2007 version 12.0.6423.100) SP2 MSO (12.0.6425.1000)
Any help here is most appreciated!
Regards
Nock
For some reason my project start and finish dates keep reverting to '1984'
based dates...e.g '1/2/1984'
Anyone know why this is happening? I've seen this behaviour in previous
versions of the product (like MSP 98) but thought this would have been
resolved in 2007.
To recreate this error.
1. Create a new task in MSP and do not specify a start and finish date
2. Attach a precedessor to the task
3. Click save
4. Delete the predecessor and voila! Dates revert to xx/xx/1984.
I've notice that this behaviour appears for some users and not others, which
is a real pain. I've worked through the differences in the MSP options but
nothing seems to stick out.
All users are using MSP 2007 version 12.0.6423.100) SP2 MSO (12.0.6425.1000)
Any help here is most appreciated!
Regards
Nock