Why it's not recommended?

M

Mario

Hi,

Why it's not recommended to use master project with
subprojects on project server 2002 ?

Thanks for your answers.

Mario
 
W

William \(Bill\) Raymond

Hi Mario,

You will find that creating master/sub projects is a very complex task to
get the data you need. For example, you should be tying those projects
together using predecessors/successors... Also, multiple people trying to
edit projects while another person has them checked out will cause confusion
and make it difficult to manage.

Just a few reasons...

-Bill
 
D

Dale Howard

Mario --

In addition to what Bill stated, publishing a master project to the Project
Server database will DOUBLE all of your resource assignments found in each
of the subprojects. Not a nice thing, indeed!

--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
G

Guest

Thanks you guys
-----Original Message-----
Mario --

In addition to what Bill stated, publishing a master project to the Project
Server database will DOUBLE all of your resource assignments found in each
of the subprojects. Not a nice thing, indeed!

--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"