T
TH2005
We are using actuals (day by day) to update the tasks. I've observed that
some tasks showing resource unit more than 1000% after I accpeted the
updates. Why? I have verified that the resource didn't enter any huge hours
for those tasks. So it's not the peak usage. It's something else? Does anyone
know why I'm seeing that big number in the Units and what would fix that
issue?
some tasks showing resource unit more than 1000% after I accpeted the
updates. Why? I have verified that the resource didn't enter any huge hours
for those tasks. So it's not the peak usage. It's something else? Does anyone
know why I'm seeing that big number in the Units and what would fix that
issue?