why the tasks are appearing on timesheet after they have completed

B

basim alvi

Hi,

Those tasks which are completed and in the timesheet notification column
TICK mark is displayed . why these tasks are not erase . because these tasks
are completed.

regards

basim alvi
 
M

mark.everett

Basim -

Current Tasks shows tasks that should have started, tasks that have
started but are not yet completed, and tasks that are due to start
within 10 days or the period set for "current tasks" by the admin.

I suspect your user(s) have "all tasks" selected. If they check on
"current tasks" they will not see the completed items.

Mark S. Everett | PMP
 
Top