T
thebehm5
I am taking a project management class and we are to enter in a diagram from
our text book. The problem occurs when we get to Task D and Task E.
Task E is predecessed by Task D in a start-start relationship with a lag
time of 2 days. Task E also has a finish-finish relationship with D with a
lag time of 2 days. When I enter this in, I get an error message.
Why won't MS-Project allow both a start-to-start and a
finish-to-finish relationship between two successive tasks?
Another quirk in this problem is that in MS-Project, Task F will not be
shown to have 12 days of start-slack. Task F, dependent on Task A in a
finish-start relationship, could start as early as day 5, after Task A is
completed, or as late as day 17, to make sure that the task is completed by
day 20.
Why does MS-Project believe that the Earliest Start Time of Task F is also
day 17? It should be day 5.
our text book. The problem occurs when we get to Task D and Task E.
Task E is predecessed by Task D in a start-start relationship with a lag
time of 2 days. Task E also has a finish-finish relationship with D with a
lag time of 2 days. When I enter this in, I get an error message.
Why won't MS-Project allow both a start-to-start and a
finish-to-finish relationship between two successive tasks?
Another quirk in this problem is that in MS-Project, Task F will not be
shown to have 12 days of start-slack. Task F, dependent on Task A in a
finish-start relationship, could start as early as day 5, after Task A is
completed, or as late as day 17, to make sure that the task is completed by
day 20.
Why does MS-Project believe that the Earliest Start Time of Task F is also
day 17? It should be day 5.