Work and Actuals disappear

J

jem

Good morning,

Has anyone ever had a problem with hours disappearing/not displaying in
Project Pro and in PWA? We have one project that will not display hours in
any view. The summary hours are there if you look at totals and statistics,
but if you look at the individual tasks, no time appears at all. It does
not display on the timesheet view in PWA either. Any suggestions?

Thank you.
jem
 
J

jem

Hi,

Yes, the project has been published several times, first with all info, then
as updated assignments are made. It is just recently that the hours have
stopped displaying. However, you can see the totals accumulating and the
remaining hours decreasing, (within the statistics).

Thanks.
jem
 