B
Brother_52
Hi,
I've just implemented Project Server as a test bed at work, specifically to
alleviate some of the resource 'black holes' that we currently have. I'm
very close to being able to prove its worth to senior management, except of
one 'small' issue, and I wondered if someone could help.
I have four projects in server at the moment, using the same enterprise
resource pool. I have created a view in Portfolio Analyser that shows
individual resource availability up to March 2006. However, I am getting the
situation where a resource can be shown as having 8 hours work allocated on a
particular day, yet the availability for that day also shows 8 hours.
Obviously, this cannot be (well, not until near the end of the programme
anyway!) - could somebody help please?
I've just implemented Project Server as a test bed at work, specifically to
alleviate some of the resource 'black holes' that we currently have. I'm
very close to being able to prove its worth to senior management, except of
one 'small' issue, and I wondered if someone could help.
I have four projects in server at the moment, using the same enterprise
resource pool. I have created a view in Portfolio Analyser that shows
individual resource availability up to March 2006. However, I am getting the
situation where a resource can be shown as having 8 hours work allocated on a
particular day, yet the availability for that day also shows 8 hours.
Obviously, this cannot be (well, not until near the end of the programme
anyway!) - could somebody help please?