Hi,
I'm using MSP 2003 Pro and I have encountered a problem
with the '% Work Complete' field. I want users to be able
to adjust this value without it affecting the 'Actual
Work' field. The Help doc says to "Clear the Updating
Task Status Updates Resource Status" in the Tools->Options-
Work Complete' value is entered. I have cleared the box
in the local project file, on the server, and in the local
default projects settings.
FYI, I'm trying to do this because sometimes people take
less (or more!) time than was scheduled to get a task
done. So I don't want the 'Actual Work' & '% Work' fields
linked together.
Thanks,
Jason
I'm using MSP 2003 Pro and I have encountered a problem
with the '% Work Complete' field. I want users to be able
to adjust this value without it affecting the 'Actual
Work' field. The Help doc says to "Clear the Updating
Task Status Updates Resource Status" in the Tools->Options-
box, the 'Actual Work' field is still adjusted when a '%Calculations menu. However, even after I uncheck the
Work Complete' value is entered. I have cleared the box
in the local project file, on the server, and in the local
default projects settings.
FYI, I'm trying to do this because sometimes people take
less (or more!) time than was scheduled to get a task
done. So I don't want the 'Actual Work' & '% Work' fields
linked together.
Thanks,
Jason