% Work Complete is 100% but % Complete is not

A

AMB

If the % Work Complete on a task 100%, why would the %Complete not be 100%?
And the remaining work for that task is at 0.

I have a plan where the task is assigned to one resource; he has entered his
time and work = actual work, remaining work is 0, %work complete is 100%...
BUT the % complete on the task is 86%.

Any ideas?
 