%Work Complete Not Being Updated in 2002 Desktop Client

M

Mike

Having a quirky issue:

1) Team members update % Work Complete on their timesheets, hit update all
2) PM accepts updates, and hits the update button
3) Desktop loads project, saves project, but doesn't seem to capture any of
the updates
4) PWA keeps the updates on the time sheet, but they do not get represented
on the Project Center view

Am using MSPS 2003 SP1 & MSP 2002 Desktop....have also gone to the FAQ site,
and clicked on the Tools / Options / Calculations / Automatically calculate
resources...
 
D

Dale Howard [MVP]

Mike --

After processing task updates into the Microsoft Project plan, do your
Microsoft Project 2002 users click Collaborate - Publish - All Information?
If not, what happens when they do this step? Let us know.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top